Talbingo NOA Management
About this project
In January 2020, the Dunns Road and Green Valley fires burnt approximately 600,000 hectares of land in the Snowy Mountains region, including Talbingo.
Following the fires and major storm events in March 2020, February 2021, and November 2022, three culvert sites in the northern Boraig-Buddong section of the Talbingo Transmission Track sustained severe damage, requiring civil repairs.
The presence of Naturally Occurring Asbestos (NOA) along the track necessitated that all civil works be coordinated and managed under friable asbestos conditions.
RARE Environmental, a licensed friable asbestos removal contractor, was engaged to develop comprehensive management strategies and assist the client in executing all civil repair works under strict asbestos controls and supervision.
How we helped
- Developed comprehensive project documentation, including detailed Asbestos Removal Control Plan (ARCP), and regulator notifications.
- Inducted workers into the project, ensuring all proposed processes and procedures complied with asbestos management standards at all stages of work.
- Established site asbestos controls, including clearly signposted asbestos exclusion zones and a decontamination trailer.
- Supervised all civil works within known NOA areas, including the coordination and execution of a capping layer along designated sections of the road.
- Conducted thorough decontamination of all plant and equipment used in the disturbance of NOA.
- Safely managed and contained all asbestos waste by securing it in 200µm waste disposal bags for controlled load-out.
- Transported all asbestos waste under EPA tracking to a licensed disposal facility.
Project Details
Client
Gracey & Sons Earthmoving
Location
Talbingo, NSW
Value
$65K
Timeline
November 2024 - ongoing